Sewer main line construction inspection checklist

Periodic, pre-pavement and final inspections of a public sewer main extension built by a developer or contractor, through to acceptance. Record test results with the acceptance testing template.

Based on: Common sewer agency development standards and specifications

Print this page for a blank field form; the website around it is left off.

Before construction

ItemPassFailN/A
Submittals (pipe, manholes, bedding, tracer wire, testing firms) approved before the preconstruction meeting
Preconstruction meeting held with the owner, engineer, contractor and foreman; inspector given the schedule and 48 hours' notice of start (typical)
Approved construction drawings on site and in use
Plug installed and anchored where the new work connects, keeping water and debris out of the existing system Photo
Existing mains, manholes and laterals near the work located and protected

Manholes

ItemPassFailN/A
Manhole base, sections and cone match the standard details; sections stacked plumb Photo
Joints sealed per specification (mastic or gasket) and pipe-to-manhole connections grouted or booted
Cores drilled cleanly where connecting to an existing manhole; inverts formed and channeled smoothly Photo
Drop and pressure-line connections built to the details, where used

Pipe

ItemPassFailN/A
Pipe, fittings and materials match the approved submittals
Grade and alignment match the approved drawings; no flat spots or reverse grade
Joints fully seated and pipe undamaged before backfill Photo
HDPE fusion joints made by a qualified operator, with internal beads removed where required

Bedding and backfill

ItemPassFailN/A
Bedding material and depth match the trench detail; haunches placed and compacted Photo
Initial backfill, tracer wire and marking tape placed as specified
Trench dikes or cutoffs installed on steep grades, where the drawings call for them

Lateral stubs

ItemPassFailN/A
Wye or tee location, stub length and slope match the drawings
Stub bedded and end-capped, with a marker post or locate at the end Photo
Low-pressure laterals: curb stop, check valve and support block installed

Utilities

ItemPassFailN/A
Separation from water lines and other utilities met at parallels and crossings
No construction debris, water or soil entering the existing system

Pre-pavement

ItemPassFailN/A
Air, vacuum, pressure and tracer wire tests and TV inspection passed and submitted before the pre-pavement inspection
Manholes, inverts and pipe clean; plywood bottoms placed in manholes before paving (typical)
Pre-pavement punch list issued and every item corrected before paving

Final

ItemPassFailN/A
Manhole frames and covers adjusted to final grade, aligned and collared Photo
Off-road manholes marked; ground graded and revegetated around them; access roads complete Photo
Lateral stub markers in place and visible
Record drawings and final tracer wire test submitted
Plugs and plywood bottoms removed with the inspector present
Final punch list issued; warranty period start date recorded

Photo A photo is expected with this item.

This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. For sewer districts and public works departments in any state: construction and acceptance of public sewer mains, private laterals and interceptors, and grease (FOG) compliance at food service businesses. Test methods follow common standards (UNI-B-6, ASTM F1417, ASTM C1244). Values marked "typical" are common values from published sewer agency standards and pretreatment rules; replace them with your own agency's standards and ordinances.

Fill it in on your phone instead.

In inspectorjay, every item gets a pass or fail, a dictated note, and geotagged photos, and the report goes to the contractor before you leave the site.