Sewer main line acceptance testing checklist

Witnessed acceptance tests on a new or modified public sewer main before paving. Note each section or manhole tested, the readings, and any failures and retests.

Based on: UNI-B-6 and ASTM F1417 (low-pressure air), ASTM C1244 (manhole vacuum)

Print this page for a blank field form; the website around it is left off.

General

ItemPassFailN/A
Inspector given notice of each test (24 hours typical); testing and TV firms approved by the agency
Lines backfilled and cleaned before testing; testing done before paving

Air test

ItemPassFailN/A
Each gravity main section (manhole to manhole) and its lateral stubs air tested per UNI-B-6 / ASTM F1417, with the pressure raised for groundwater above the pipe
Gauge range suitable (no gauges reading over 30 psi, typical); pressure held for the time the standard sets for the pipe size and length

Hydrostatic test

ItemPassFailN/A
Force mains and low-pressure mains flushed with the inspector present before testing
Tested at the greater of 150% of design pressure or 100 psi for 2 hours (typical); air expelled first
Leakage below the allowable (typical: Q = L x D x sqrt(P) / 133,200 gal/hr), and any visible leak repaired regardless

Manhole vacuum

ItemPassFailN/A
Each manhole vacuum tested per ASTM C1244 to the top of the cone or flat slab, and held for the time the standard sets for its size

Deflection

ItemPassFailN/A
Flexible pipe mandrel tested at 95% of inside diameter, at least 30 days after final backfill, pulled by hand (typical; where the agency requires it)

TV inspection

ItemPassFailN/A
Every main section, stub and new manhole televised after the other tests pass, with water running and the line clean
Video labeled with project, date, direction, start and end footage, pipe type and size, lateral locations and defects
No bellies, flat or reverse grade, debris, damaged or displaced joints, bad wyes, bad manhole connections or infiltration

Tracer wire

ItemPassFailN/A
Tracer wire continuity tested after backfill and again before final acceptance

HDPE

ItemPassFailN/A
Extracted internal fusion beads inspected: fully removed, double roll-back shape, smooth root cut

Compaction

ItemPassFailN/A
Compaction tests taken at the specified frequency (typical: 1 per lift per 200 ft off-road, 1 per 200 ft of bedding)

Pump station

ItemPassFailN/A
Pump station run continuously for 72 hours on clear water without failure, every valve and control operated (typical)
Electrical and controls tested per NETA and the manufacturers

Results

ItemPassFailN/A
Each item's pass, failure, reason and retest recorded on the test results form and submitted
Failed sections repaired by approved methods (no surface grouting of manhole sections) and retested to a pass

Photo A photo is expected with this item.

This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. For sewer districts and public works departments in any state: construction and acceptance of public sewer mains, private laterals and interceptors, and grease (FOG) compliance at food service businesses. Test methods follow common standards (UNI-B-6, ASTM F1417, ASTM C1244). Values marked "typical" are common values from published sewer agency standards and pretreatment rules; replace them with your own agency's standards and ordinances.