Rhode Island post-storm inspection checklist
Follow-up after a storm that causes runoff, or the storm size the permit names, focused on where water went and what controls failed.
Based on: RIDEM RIPDES Construction General Permit: inspection and corrective action requirements
Print this page for a blank field form; the website around it is left off.
Storm
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Rainfall amount and date recorded (site rain gauge or the weather station named in the SESC Plan) | |||
| Inspection made within the time the permit allows after the storm, or the reason it wasn't |
Discharges
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Each discharge point observed; any sediment, turbidity or sheen described Photo | |||
| Receiving water or storm drain downstream checked for sediment deposits |
Controls
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Perimeter controls intact after the storm: no breaches, undercutting or overtopping Photo | |||
| Inlet protection intact and not clogged; sediment removed Photo | |||
| Sediment basins and traps have capacity for the next storm | |||
| Track-out cleaned from streets after the storm | |||
| Slopes and stabilized areas free of new rills and gullies | |||
| Washouts and stockpiles not washed out or overflowing |
Follow-up
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Every failure found entered as a corrective action with a fix date |
Photo A photo is expected with this item.
Skip the clipboard next time. Scan to try this inspection on your phone in the inspectorjay demo: geotagged photos, dictated notes, a pass or fail on every item, and the report emailed to the contractor before you leave the site.
demo.inspectorjay.com/app · inspectorjay.com
This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. Based on the RIDEM RIPDES Construction General Permit and the Rhode Island Soil Erosion and Sediment Control Handbook. The plan is the Soil Erosion and Sediment Control (SESC) Plan. Check each template against the current permit and your local requirements before relying on it.
Know when these checklists change
Permits get renewed and their requirements move. Leave your email and we'll tell you when we update the Rhode Island checklists or add new ones. A few emails a year at most.
You're on the list. We'll email you when the Rhode Island checklists change.
That didn't go through. Check your email address and try again, or write to hello@inspectorjay.com.
Fill it in on your phone instead.
In inspectorjay, every item gets a pass or fail, a dictated note, and geotagged photos, and the report goes to the contractor before you leave the site.