Maryland 20-CP site inspection checklist

Routine stormwater inspection of an active construction site, from the entrance to the perimeter to the interior. For the operator's scheduled inspections and for MS4 or county oversight visits.

Based on: MDE General Permit for Stormwater Associated with Construction Activity (20-CP)

Print this page for a blank field form; the website around it is left off.

Entrance

ItemPassFailN/A
Permit coverage posted at the entrance where the public can read it, with the permit or authorization number, a contact, and where to see the approved erosion and sediment control plan
Approved erosion and sediment control plan on site, or available as the permit allows, and current
Streets and sidewalks next to the site free of tracked mud and sediment Photo
Stabilized construction exits (stone pads, rumble plates, wheel wash) at every exit and maintained Photo

Perimeter

ItemPassFailN/A
Perimeter controls (silt fence, wattles, berms) installed per the approved erosion and sediment control plan, intact, and not overtopped Photo
Sediment behind perimeter controls removed before it builds up to half their height
Buffers to streams, wetlands and other waters kept, or equivalent controls in place
Velocity dissipation at outlets and along channels; no scour or erosion
No sediment or other pollutants visibly leaving the site at any discharge point Photo
Controls installed to the 2011 Maryland Standards and Specifications and the approved plan

Interior

ItemPassFailN/A
Storm drain inlets on and next to the site protected, and sediment around them removed Photo
Soil and material stockpiles covered or contained, and away from inlets and conveyances
Dust controlled on exposed soil and haul roads
Stabilization within the plan's deadlines (3 days for perimeter controls and slopes steeper than 3:1, 7 days for other disturbed areas)
Sediment basins and traps working, with storage capacity left
Dewatering water treated before discharge; no turbid water pumped off the site

Pollution prevention

ItemPassFailN/A
Fueling, maintenance and equipment washing areas have spill prevention and containment
Chemicals and hazardous materials stored with secondary containment and cover
No spills or leaks; any spill contained and cleaned up Photo
Trash and construction debris contained, covered and emptied before overflowing
Portable toilets secured, away from inlets and drainage, and not leaking
Concrete, stucco and paint washout contained, not leaking, and below capacity Photo

Records

ItemPassFailN/A
Inspections done at the frequency the permit and approved erosion and sediment control plan set, including the inspections required after storms
Responsible personnel on site hold MDE Responsible Personnel Certification (green card)
Corrective actions from earlier inspections logged and fixed or scheduled on time
Approved erosion and sediment control plan site map shows the BMPs as they are installed today

Photo A photo is expected with this item.

This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. Based on the MDE General Permit for Stormwater Associated with Construction Activity (20-CP) and the 2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control. Check each template against the current permit and your local requirements before relying on it.

Fill it in on your phone instead.

In inspectorjay, every item gets a pass or fail, a dictated note, and geotagged photos, and the report goes to the contractor before you leave the site.