Alabama post-storm inspection (0.75 in. or more in 24 hours) checklist
Follow-up after a storm of 0.75 in. or more in 24 hours, focused on where water went and what controls failed.
Based on: ADEM NPDES General Permit ALR100000 and ADEM Admin. Code ch. 335-6-12 (inspections in rule 335-6-12-.28): inspection and corrective action requirements
Print this page for a blank field form; the website around it is left off.
Storm
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Rainfall amount and date recorded (site rain gauge or the weather station named in the CBMPP) | |||
| Inspection started within 48 hours after work resumes and completed within 72 hours of the qualifying event, or the reason it wasn't |
Discharges
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Each discharge point observed; any sediment, turbidity or sheen described Photo | |||
| Receiving water or storm drain downstream checked for sediment deposits |
Controls
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Perimeter controls intact after the storm: no breaches, undercutting or overtopping Photo | |||
| Inlet protection intact and not clogged; sediment removed Photo | |||
| Sediment basins and traps have capacity for the next storm | |||
| Track-out cleaned from streets after the storm | |||
| Slopes and stabilized areas free of new rills and gullies | |||
| Washouts and stockpiles not washed out or overflowing |
Follow-up
| Item | Pass | Fail | N/A |
|---|---|---|---|
| Every failure found entered as a corrective action with a fix date |
Photo A photo is expected with this item.
Skip the clipboard next time. Scan to try this inspection on your phone in the inspectorjay demo: geotagged photos, dictated notes, a pass or fail on every item, and the report emailed to the contractor before you leave the site.
demo.inspectorjay.com/app · inspectorjay.com
This checklist is a starting point. Check each item against your current permit and your agency's standards before relying on it. Based on the ADEM NPDES General Permit ALR100000 for construction, small mining and land disturbance (ADEM Admin. Code ch. 335-6-12), which calls the SWPPP a Construction Best Management Practices Plan (CBMPP). Check each template against the current permit and your local requirements before relying on it.
Know when these checklists change
Permits get renewed and their requirements move. Leave your email and we'll tell you when we update the Alabama checklists or add new ones. A few emails a year at most.
You're on the list. We'll email you when the Alabama checklists change.
That didn't go through. Check your email address and try again, or write to hello@inspectorjay.com.
Fill it in on your phone instead.
In inspectorjay, every item gets a pass or fail, a dictated note, and geotagged photos, and the report goes to the contractor before you leave the site.